CA Drillers worked with BAM Nuttall to deliver concrete cutting and sawing services for the airport’s development project. Our job required precise operations in challenging locations, which we achieved on time and with high-quality results, earning us to be shortlisted for an award by The International Association of Concrete Drillers & Sawers.
Due to tight schedule constraints centred around the piling contractor, a daily requirement existed for cutting 80 linear metres (600 mm / 700 mm deep). To meet this demanding timeline, we had to consider installing 40 metres of track at a time with two saws operating concurrently. This was achieved while working from a barge and implementing rigorous water management measures to contain the substantial amounts of water/slurry generated, as, for environmental reasons, it was imperative to prevent contamination of the water within The King George V Dock.
Our cut line was positioned 200mm above the water level, adding significant complexity, particularly since we had to cope with the constant motion of the working barge. Another challenge we faced was that the protective measures used had to be removable daily to accommodate the arrival of the night barge, which was tasked with lifting the cut concrete sections.
Our final solution involved the installation of a 150mm steel guttering system beneath the cut line. This system was installed in 20m sections in both directions, each with a very slight incline, leading into a specially designed container. The resulting waste water/slurry was then pumped into 1000-litre IBC containers located on the barge. These were removed each evening for recycling through a silt buster
In August 2019, the CA Drillers team started restoration project at the Old War Office, an iconic site nestled in the heart of Westminster. As the project progressed, our team expanded, reaching a robust strength of 60 skilled operatives during its most demanding phase. This ambitious endeavour was brought to a successful completion in October 2023.
Our extensive scope of work showcased our versatility and expertise in a variety of challenging tasks. This included the diamond drilling of substantial sump pits in the basement areas, complemented by the advanced use of Brokk demolition robots for efficient break-out operations. In the swimming pool area, we undertook precise core drilling to accommodate lighting installations, blending functionality with aesthetic considerations.
Furthermore, our team formed builders’ work openings, employing both hand saws and track saws, coupled with stitch drilling techniques to avoid overcutting. Followed by the installation of lintels was carried out with across all levels, reinforcing the framework of the building. In adherence to stringent health and safety measures, we implemented control measures in our work areas which included full tent enclosures, chapter 8 barriers for demarcation, and dust cubes for effective extraction of any dust generated during our operations.
Our responsibilities also extended to complex tasks such as forming rainwater pipes, a challenging process that began at the roof and involved cutting and breaking through walls and slabs, down to the fourth basement level. Additionally, we were tasked with the intricate chasing of electrical conduits within the ceilings, slabs, and walls throughout the entire building.
A particularly challenging aspect of our work involved the wire saw removal of steel-plated, bomb-proof walls encircling the building. The scale and diversity of our work package not only demonstrated our technical prowess but also our dedication to preserving and enhancing a building that is a symbol of British heritage. CA Drillers takes immense pride in having played a pivotal role in the restoration of this venerable landmark, contributing to the conservation of its rich history and architectural grandeur.
CA Drillers established site in September 2021, our first task was the deconstruction of the River Wall. This challenging task required the implementation of vertical stitch drilling from the landside to sever the wall into detachable sections and subsequently be lifted out by the aid of Riverlinx machines. To ensure the River Thames, located underneath, remained free of slurry produced by the drilling and sawing, strict water and slurry control measures were employed.
Following that, we performed a series of operations on multiple areas on site. We have carried out floor sawing activities critical for initiating the open-cut procedure of the tunnel’s construction. Wire sawing was also conducted on existing UAE structures. Furthermore, we carried out a large quantity of pile cropping, we trimmed the pile tops to the necessary height using an effective combination of track sawing and Brokk demolition. It was essential that we was to retain the rebar within and not cause any damage, therefore the track sawing and Brokk activities was carried out with due diligence as to negate affecting the integrity of the rebar.
In addition, we was awarded the scope of works to demolish the Victorian dock wall which obstructed the trajectory path of the tunnel. For this, we employed a Brokk 400 & Brokk 800, to carry out the heavy duty demolition task. More recently, we were involved in the headwall cut and carve operation. This operation was vital to prepare for the Tunnel Boring Machine (TBM)’s departure from Silvertown to Greenwich. This stage was a pivotal moment in the project, as it is when the TBM made its initial breakthrough at Greenwich after setting off from Silvertown, effectively forming the initial tunnel wall. In order to facilitate the Tunnel Boring Machine (TBM)’s successful exit, we employed a drilling and sawing approach.
This involved creating a series of drill holes around the circumference of the TBM machine and making vertical track saw cuts. The primary aim of this intricate operation was to weaken the structural stability of the wall. By doing so, we enabled the TBM to successfully penetrate and bore through the wall. This operation required meticulous planning and flawless execution, all of which were crucial in ensuring the TBM’s successful journey to Greenwich. We was provided short notice and time frame to start and complete. We received the phone call on a Friday with the intent to mobilise site on the Sunday and all works completed within the time frame of Wednesday. This achievement was a testament to our team’s dedication, expertise, and commitment to delivering high-quality work on schedule. (Please see pics below of the headwall cut and carve).
At the onset, C A Drillers undertook specific assignments for the Space House project, which included making track saw cuts on 48 concrete T units within PAYE’s yard. These intricate tasks demanded heavy-duty cutting and drilling. Each unit required a 3m x 450mm deep track saw cut, a 3m x 750mm deep track saw cut, and a central stitch drill to separate the 3m x 750mm x 450mm section.
Once cut, these units were lifted by the on-site crane and redistributed. Due to certain time restrictions, PAYE made accommodations for additional T units in the yard, consequently amplifying the productivity expected from CA in order to ensure compliance with the project’s schedule. Despite these demands, the team completed the tasks within the set timeframe. Following this initial phase, CA relocated to the Space House site where they were tasked with trimming back lift shaft slabs and executing necessary concrete repairs. Considering the tasks were to be carried out within a lift shaft, operatives ensured the implementation of adequate safety measures to mitigate risk from falling debris.
Activities within the lift shaft were managed with multiple layers of corex to reduce the amount of debris. This careful breakout of the slab also allowed for efficient debris clearance. Additionally, the concrete repair works within the lift shaft were thoroughly documented by the C A site manager through quality assurance documents. These were countersigned by BAM management to verify that all repairs were conducted to their specifications.
In the subsequent stages, C A has carried out a host of diverse tasks around the site. These tasks range from prepping the floors throughout the entire building, lowering the slab level to assist the screed applicators in their work, employing our Brokk robots to chip away at the screed in B2, stitch drilling riser openings across every floor, and creating numerous openings and core holes through both the slab and wall for M&E and ductwork facilitation. Our team continues to work diligently on site, delivering high-quality results and readily accommodating the site team’s requests, irrespective of the given time constraints. For quality control and safety assurance, our contracts manager and health & safety manager conduct either weekly or bi-weekly site visits, undertaking on-site briefings and carrying out safety walkarounds with the C A site team.
CA Drillers commenced a significant project at 105 Victoria in November 2022, working in closely with the Erith Group to safely perform a variety of demolition tasks, including intricate cut and carve operations. This includes the stitch drilling of pile openings to a depth of 1.5 meters and the subsequent lifting of large segments using A-frames.
We also carried out track sawing to form trenches that are 1 meter deep, which were then efficiently broken out using a pair of robust Brokk 400 machines. Our expertise extended to diamond drilling, creating 600mm diameter holes to a depth of 600mm, which was then broken back to create slots for the installation of new steel wailers.
Additionally, we have undertaken tasks involving track sawing for creating corner holes and employing Brokk machines for demolishing sections of a small roof. Furthermore, the operatives used the specialised munching jaw and sheathe attachment of the Brokk machines in removing the roof, effectively reducing the risk of flying debris and limiting vibration transmission through the structure.
Our ongoing efforts include extensive track sawing and floor sawing in the basement levels’ structural slab. This range of work undertaken at the site reflects our standing as a leading specialist drilling and sawing company, particularly skilled in cut and carve techniques. This assertion is supported by our track record on this project.
Crossrail is building the Elizabeth line – a new railway for London and the South East, running from Reading and Heathrow in the west, through 42km of new tunnels under London to Shenfield and Abbey Wood in the east. The Crossrail project is Europe’s largest infrastructure project with a value of £15.4bn.
CA Drillers started works within the newly constructed tunnel in June 2016. Our initial scope was to complete some intricate cutting works within a cross passage and then complete with a concrete repair. Our works quickly escalated to drilling 1000’s holes for cable containment, fire mains and the emergency walkway system to track sawing 100’s of meters of reinforced concrete to the management and overseeing the installation of 955m2 of the screed. Over 50,000 manholes were completed on-site without a single incident or accident giving us one of the best health and safety records on the project.
The former Port of London Authority headquarters at 10 Trinity Square has been reborn as the Square Mile’s first “super luxury” hotel and residences. The grade II* listed building and three-acre site next to the Tower of London in the City was formed into a 120-bedroom hotel with 37 private apartments designed by David Collins, as well as an exclusive private members’ club, three restaurants and a spa.
CA Drillers aspect of the works involved controlled demolition using Brokk robotic machines, diamond drilling, diamond wire sawing & diamond track sawing. From demolishing the entire basement swimming pool to 1000’s holes across the site all works were completed to our usual high standard.
This site in the City of Westminster was originally owned by the British Army. The £3bn development won local-government approval in 2011 to develop almost 450 homes, stores, a health centre and leisure facilities on the 13-acre site which is due for completion in 2024. Buyers of some of the homes sold are reported to be paying £4500 per square foot which makes these properties some of the most expensive in London! The size and logistics of this vast project were always going to be one of the main challenges on this flagship job.
To ensure our service was up to our high usual standard, we set up an office and stores on site so that we always had the manpower and equipment to complete all required works. From our initial start in May 2016, we completed a wide variety of services on this project ranging from diamond drilling for pipework and ductwork, diamond track sawing for lift shafts to using Brokk’s to demolish concrete piles.
We started working on this site for Costain on behalf of Crossrail in August 2014 and completed our works in November 2018. Paddington New Yard, located between the Westbourne Park Tube station and Paddington National Rail station, contains both the Royal Oak Portal and Westbourne Park Crossrail worksites.
The contract included the construction of a new 180m long elevated bus deck which connected Westbourne Park Bus Garage, the relocation of an existing concrete batching plant, and preparatory works for the installation of new rail track and associated systems for Crossrail in Paddington New Yard. Due to the majority of the site running over the Crossrail tunnel, heavy breaking was not allowed due to vibration concerns. A large amount of concrete required removing which was completed using diamond floor sawing, diamond track sawing and hydraulic bursting techniques. Works were completed on time and on budget.
Part of the Tower 42 Estate, this high-quality mixed-use development replaced and expanded the existing accommodation and enhanced the public realm. 15 Bishopsgate provided a six-story office building with retail at ground and basement level that edged the re-landscaped public areas. We were heavily involved with the enabling works on this project due to the sensitive nature of existing buildings with vibration being kept to a minimum.
Areas that would usually be broken out with heavy machinery were track and wire sawn into manageable sections before being removed from the site. Inverted track sawing was engaged due to access issues along with cutting through 800mm deep heavily reinforced concrete. All works ran smoothly with 2 track saws and 1 wire saw permanently on-site to ensure we could react quickly to any last-minute requests.
Find Out How Our Expertise Can Help You By Calling
CA DRILLERS ON
08009750891